Cloud Migration

Cloud Migration Program

Infrastructure

A staged cutover off a single on-prem host onto managed cloud with rollback paths, not a weekend big-bang.

Outcome Snapshot
-40%

Unplanned Downtime

Prod + staging isolated

Environments

< 30 min

Rollback Window

Project Snapshot

Delivery Context And Business Outcome

Industry

Operations software

Duration

12 weeks

Technology Stack

Containers, managed database, CI/CD

Key Outcome

Cutover with a named rollback, not a hope-and-pray DNS flip
Project Context

Client Industry, Timeline, Team, Stack, And Result

Client Industry

Operations software

Project Timeline

12 weeks

Team Size

6 specialists

Tech Stack

Containers, managed database, CI/CD

Headline Result

Cutover with a named rollback, not a hope-and-pray DNS flip

Project Foundation

Problem Statement, Baseline, And Success Criteria

Clear pre-project constraints and measurable targets establish how outcomes are evaluated.

Problem Statement

The live system sat on one machine with no staging twin.

Goals And Success Criteria

Unplanned Downtime (Target)60 index
Environments (Target)Prod + staging isolated
Rollback Window (Target)< 30 min
Baseline Metrics

Where Performance Started Before Delivery

Unplanned Downtime (Before)

100 index

Environments (Before)

100 index

Rollback Window (Before)

100 index
Business Overview

What The Engagement Needed To Deliver

Infinoid moved a production workload to cloud in slices: data, then stateless services, then DNS — each with a measured rollback.

Cloud migration cutover board
Solution Preview

Cloud migration cutover board

Process Timeline

Discovery To Optimization With Duration

Discovery

1-2 weeks

Stakeholder interviews, baseline audit, and scope alignment.

Design

1-2 weeks

UX flows, technical architecture, and sprint planning.

Build

4-8 weeks

Incremental feature delivery, integrations, and instrumentation.

QA

1-2 weeks

Functional testing, performance validation, and accessibility checks.

Launch

3-5 days

Controlled release, production validation, and monitoring.

Optimization

2-4 weeks

Post-launch iteration based on telemetry and user feedback.

Challenges And Solutions

How The Product Direction Was Resolved

Key Challenges

Single Host Risk

The live system sat on one machine with no staging twin.

Unclear Data Size

Nobody had measured how long a restore actually took.

Vendor Lock Fear

The team needed a path that did not require rewriting the product first.

Implemented Solutions

Built a staging environment that matched production enough to rehearse cutover.

Moved data with checksums and a timed restore drill before touching DNS.

Automated deploys so the next change did not require the same heroics.

Key Decisions And Tradeoffs

Why This Approach Was Chosen

Built A Staging Environment That Matched Production Enough To Rehearse Cutover.

Tradeoff: Single host risk

Rationale: Selected for long-term scalability, maintainability, and stronger business outcomes.

Moved Data With Checksums And A Timed Restore Drill Before Touching DNS.

Tradeoff: Unclear data size

Rationale: Selected for long-term scalability, maintainability, and stronger business outcomes.

Automated Deploys So The Next Change Did Not Require The Same Heroics.

Tradeoff: Vendor lock fear

Rationale: Selected for long-term scalability, maintainability, and stronger business outcomes.

Measured Results

Before And After Comparison With Hard Numbers

MetricBeforeAfterDelta
Unplanned Downtime100 index60 index-40%
Environments100 indexProd + staging isolatedProd + staging isolated
Rollback Window100 index< 30 min< 30 min
SEO, Performance, Accessibility

Technical Outcomes After Launch

Lighthouse Performance

+20 points

Core Web Vitals

LCP -30%, CLS < 0.1

Accessibility Score

+15 points
Results And Impact

What We'd Improve Next

Continuous Improvement Opportunities

Expand A/B testing coverage for high-traffic user journeys.

Add deeper event-level analytics for conversion funnels.

Extend automation around regression and accessibility audits.

Next step

Planning A Cutover, Not A Slide Deck?

Share what is on-prem today. We will propose a first slice with a rollback, from the Noida desk.

What we cover

  • 01

    Named delivery from the Noida desk

  • 02

    Integrations against systems you already run

  • 03

    Hire dedicated engineers if you need people on your cadence

Typical first call · 30–45 min